Chlorinated Sea Water is a vital utility
service which provides uninterrupted supply of seawater
for non-contact process cooling applications to the
industries in the Sohar Industrial Port Area.
The Sea Water Intake and Return System-1 (SWIRS-1) is
designed to produce approximately 334,000 cubic meters
per hour of screened chlorinated seawater for distribution
at the pumping station.
With SWIRS-1 almost fully allocated to off-takers we
are on the way to build SWIRS-2 to produce approximately
an additional 324,000 cubic meters per hour of chlorinated
sea water. SWIRS-2 is expected to be commissioned by
mid 2009.
For smaller volume customers a delivery
network is being built through which sea
water will be pumped and made available at the battery
limit of industries.

The SWIRS design allows for smooth flow
of seawater through a dredged canal built between two
break water with a total length of 1800 meters and stretched
600 meters into the sea .Approximately 1 million tone
of stones has been used in the construction of the break
water and about 380,000 cubic meter of dredged material
was removed from the intake. Due to the rapid development
in the Sohar Industrial Port Area, provision for future
demand was considered by way of widening the channel
during the construction of the break water to accommodate
another pumping station. The existing Intake capacity
is approximately 700,000m3/hr which is sufficient to
satisfy projected demand requirements.
An oil boom barrier placed at the mouth of the intake
prevents the ingress of any spilled oil along with the
seawater boom entering the pumping station.

The design allows a smooth inflow of seawater
through screening chambers. These act as filters to
keep marine life out of the pumping station. As a backup
measure, Hypo chlorite solution is continuously injected
into the inflow of water. The strong solution kills
any marine life that escapes the screening chambers.
They have 10 screening chambers each with
one rake bar and one band screen. Four screen bays are
placed in the centre while three are on either side.
The water passes through rake bars and
reaches a section fitted with screen bars spaced at
30 millimeters, which block passage of dead marine life
and waste material.
Distribution
bays supply water to 48 pump chambers allotted to 13
Users in 12 different corridors. Each pump chamber can
draw water up to a maximum of 16,000 cubic meters per
hour. The width of each chamber is 4 meter.
Water enters the four distribution bays where baffle
walls eliminate the formation of eddies and swirls and
regulates the water flowing towards pump chambers.
A Chlorine production and injection station
with a production capacity of 702 kg/Hour of hypochlorite
solution is constructed to provide the required chlorine
for the processing and disinfection of the seawater.
The station is equipped with 8 lines of hypochlorite
production generators consisting of a transformer, rectifier
and electrolyser.
The hypochlorite solution is injected
automatically as per the required concentration. Online
measurement and monitoring equipment are installed and
connected to the control room to allow proper data management.
The pumping station is equipped with buildings
to facilitate the operations of the facility. Administration
offices, control and inspection rooms are in place together
with a special structure to maintain giant dam board
that could weigh up to 7400 Kg.
The system is equipped with instrumentation
facilities to allow continuous monitoring of the difference
in the level of natural seawater.
The return is by way of routing through
a Open Seawater Canal to the Return System(s) at the
coastline. Environmental Impact assessment studies have
been carried out to ensure that there are no adverse
effects to the environment. In compliance with environment
rules and regulation, Industries are not allowed to
discharge water at temperature higher then 10°C
from intake water, or to discharge any other water different
in its specification from the seawater quality.
As an integral part of the development
of the design for the intake pumping station an investigation
involving the use of a physical model was carried out
in order to evaluate the hydraulic performance of the
proposed pumping arrangement. Studies also include computational
modeling of sediment transport and wave disturbance
in the intake. Assessment of the impact on the local
shoreline as a result of the construction of the SWIRS
and a thermal dispersion simulations was carried out
in order to assess compliance of the discharge with
the Oman environmental standard.
The project faces
sudden attacks continually from hundreds of tons of
jellyfish. Colonies of jellyfish clog the screens and
mechanical parts leading to a total shutdown of the
pumping station as well as the industries. But the unique
design of this project provides a contingency plan to
prevent such jellyfish ingress. During an attack, the
speed of the rake bar screens is increased according
to its intensity. Like all other waste, the jellyfish
are collected in the trash channel and are chopped and
collected in the solid handling area. The waste is then
disposed off in a pre-designated area.
Chlorinated
Sea Water Delivered through Network
For customers requiring
smaller volumes of sea water, MISC is building
pumping facilities with a network
to supply chlorinated sea water at their battery
limit.
The network
will have a capacity to deliver 57,175 m3/hr of
chlorinated sea water and is expected to be commissioned
by January 2008. |
|